Water Treatment Plant
The City of Fort Lauderdale is committed to the delivery of clear, safe potable water to all Fort Lauderdale residents, businesses, and customers from surrounding municipalities now and in the future. To this end, the City is advancing efforts to replace the Fiveash Water Treatment Plant with the Prospect Lake Clean Water Center, a new, state-of-the-art facility, under a comprehensive agreement with the IDE-Ridgewood Project Team (Project Company).
The new plant, which is expected to be completed in 2026 with an approximate cost of $666 million including enabling works, will deliver clear, clean water and is designed to withstand the winds of a Category 5 hurricane.
The City will maintain ownership of the Prospect Lake Clean Water Center throughout construction and the following 30-year operational period with Project Company responsible for on-site operational management, maintenance and repairs. The City will coordinate operation within the water distribution system and City staff will operate the plant in partnership with on-site technical and operational resources from Project Company.
Prospect Lake Clean Water Center
Frequently Asked Questions
Find answers about the new clean water center, the Fiveash transition, water quality, customer rates and facility operations.
01When will the new Prospect Lake Clean Water Center (PLCWC) go into service?
The new Prospect Lake Clean Water Center (PLCWC) is currently being constructed under a Public Private Partnership (P3) between the City and the "Project Company." The PLCWC is currently being commissioned, meaning it is being functionally tested, while construction is finalized.
The PLCWC will begin sending water to the Fiveash Water Treatment Plant for storage and distribution to the City's customers in September 2026.
02Who is Project Company?
Project Company is the term used in the Comprehensive Agreement to identify the private entity responsible for delivering the PLCWC project. Under the Public-Private Partnership (P3) structure, this entity is accountable for the facility's design, permitting, construction and operation.
The Project Company is comprised of Ridgewood Infrastructure, a U.S.-based investor in essential infrastructure, and IDE, a world-renowned designer and operator of advanced water treatment plants.
03Why does the Fiveash Water Treatment Plant need to be replaced?
The Fiveash Water Treatment Plant, built in 1953 and expanded several times over the past 70 years, was not designed to current hurricane-force wind resistance standards and is vulnerable during extreme weather events. Its lime-softening technology cannot meet the City's goal of achieving fewer than five color units, which can result in a yellow tinge in the treated water.
In addition, most plant components are near the end of their useful life and require capital investment to remain operational. The existing technology is also ineffective at removing emerging contaminants such as PFAS and would require major upgrades to meet PFAS regulatory requirements.
04Why move location?
The PLCWC is being constructed at the Prospect Wellfield, located roughly three miles from the existing Fiveash Water Treatment Plant. The Fiveash site does not have sufficient space to accommodate construction of a new facility.
In addition, the existing plant must remain fully operational throughout the construction period to ensure uninterrupted water service, making on-site replacement impossible.
05What will happen to the Fiveash plant?
The treatment infrastructure at Fiveash will be decommissioned. The facility will transition into a storage and distribution center, storing water produced by the PLCWC and pumping it directly into the City's water distribution system to serve customers.
06Will the public have access to the site?
The PLCWC is located within the Prospect Wellfield site. Prospect Wellfield is restricted to official City use due to critical infrastructure security requirements.
07How will customer rates be impacted?
Customer rates directly support the infrastructure required to deliver safe, clean water. To fund critical modernizations like the Prospect Lake Clean Water Center, the City implemented a structured rate schedule.
Water and wastewater rates will see a 9% annual adjustment through 2027 to cover intensive infrastructure investments, before leveling off to a steady 5% annual adjustment beginning in 2028 to support ongoing operations.
08Has the City been communicating and coordinating with other municipalities that are currently being supplied by Fiveash?
Yes. Continuous regional coordination is a core priority. The City provides drinking water to multiple neighboring municipalities and large utilities across Broward County.
We are actively communicating with all our wholesale customers to coordinate the transition from the Fiveash Water Treatment Plant to the new PLCWC facility. This coordination ensures that municipal partners are fully aligned so that we can guarantee an uninterrupted water supply for the entire regional service area.
09Do we know what the anticipated noise level is for the new plant when operating at full capacity?
Yes. The new plant will operate quietly. A comprehensive noise study conducted during the design phase confirms that anticipated noise levels at the facility will easily meet City ordinances and blend into the existing background environment due to features such as built-in structural sound barriers and strategic equipment placement.
10Will this new treatment plant remove the tannins from the water which gives it a yellow tinge?
11Are the contract documents available for review by the public?
Yes. Project documents and related Commission presentations are available for public review on the City's project website.
12What can we expect during startup of the PLCWC?
City customers may notice some slight variability in taste, temporary color or cloudiness during the transition from lime-softened water to membrane/ion exchange water in the last few months of 2026 until the PLCWC is fully transitioned into service.
The variability will not affect water safety.
13What will happen to the City employees at Fiveash WTP?
Certain employees will remain at Fiveash to operate and maintain the tanks and high service pumps. Other employees are presently being trained to operate and maintain PLCWC.
14What will happen to the Peele-Dixie Membrane Plant?
The City will continue operations of the Peele-Dixie Membrane Plant, which provides treated water to the south part of the City, below Davie Boulevard.
For additional information, here's a list of important project documents:
City Commission Meeting June 3, 2025
City Commission Meeting February 18, 2025
City Commission Meeting October 1, 2024
City Commission Meeting December 19, 2023
City Commission Meeting November 7, 2023
City Commission Meeting October 3, 2023
City Commission Meeting September 19, 2023
City Commission Meeting February 21, 2023
City Commission Meeting February 7, 2023
City Commission Joint Workshop with Infrastructure Task Force January 10, 2023
- Commission Agenda Memo #23-0059
- Presentation 1 – Fiveash Water Treatment Plant Replacement
- Presentation 2 – Prospect Lake Water Treatment Plant
- Memorandum 23-001, Prospect Lake Water Treatment Plant January 4, 2023
- Attachment to Memorandum 23-001, Prospect Lake Water Treatment Plant Draft Comprehensive Agreement January 4, 2023
City Commission Conference Meeting December 6, 2022
City Commission Conference Meeting September 6, 2022
City Commission Meeting May 3, 2022
City Commission Meeting March 1, 2022
City Commission Conference Meeting January 18, 2022
City Commission Meeting March 1, 2022